Key technology of the top down construction method for oversize deep foundation pit
Author:
Affiliation:

Wuhan Geological Survey Foundation Engineering Co., Ltd., Wuhan Hubei 430000, China

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    武汉南国中心一期基坑支护工程采用逆作法施工,周边环境复杂,场区内砂层较厚,基坑设计技术要求高,特别是支护结构地下连续墙、立柱桩垂直度要求高、嵌岩深,施工时在软硬互层部位容易产生偏斜,入岩效率低。针对工程施工重难点,从设备选型、工艺选择、钻头选用等方面采取措施,解决逆作法超深超大基坑支护结构施工中的困难问题,介绍了解决问题的思路,取得了显著的效果,施工质量满足相关技术要求。

    Abstract:

    The foundation pit support works for the Wuhan Nanguo Center first phase project was constructed using the top down construction method, where the surrounding environment was complex, and the sand layer at the site is thick. The technical requirements for foundation pit design were high, in particular, the verticality of the diaphragm wall and column pile of the support structure was high with deep rock embedment. The soft and hard alternate formation tended to produce deviation during construction with low rock penetration efficiency. In view of the major and difficult points in construction, measures were taken from the aspects of equipment selection, process selection, bit selection, etc. to solve the difficulties in the construction of the super deep and large foundation pit support structure by the top down method. The approach to solving the problems was introduced, and significant results were achieved with the quality meeting the relevant technical requirements.

    参考文献
    相似文献
    引证文献
引用本文

钟 明,曾纪文,贺 浩.超深超大深基坑逆作法施工关键技术[J].钻探工程,2020,47(6):73-78.
Zhong Ming, Zeng Jiwen, He Hao. Key technology of the top down construction method for oversize deep foundation pit[J]. Drilling Engineering, 2020,47(6):73-78.