矿山投料井施工难点与对策
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD262.1; P634.5

基金项目:


Difficulties of Feeding Batching Mine Construction and the Countermeasures
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    结合福建省武平某银多金属矿施工填充站TZK1、TZK2投料井工程,详细介绍了矿山投料井施工的难点与对策:通过对钻探设备的优化组合,结合钟摆钻具原理,辅以护壁堵漏,研制分离式注浆专用阀,顺利下入套管及注浆固井,圆满完成了该投料井工程的施工任务。

    Abstract:

    The paper detailed the difficulties of feeding batching mine construction and the countermeasures according to the feeding batching mine engineering practice of TZK1 and TZK2 in Fujian. By the optimum combination of drilling equipments, based on the pendulum assembly principle, assisted by wall protection & leakage stoppage, with the development of separation-type grouting valve, the construction was fulfilled with case setting and grouting cementation.

    参考文献
    相似文献
    引证文献
引用本文

邱文权,彭金灶,陈惠明,等.矿山投料井施工难点与对策[J].钻探工程,2010,37(4):31-33.
QIU Wenquan, PENG Jin-zao, CHEN Hui-ming, et al. Difficulties of Feeding Batching Mine Construction and the Countermeasures[J]. Drilling Engineering, 2010,37(4):31-33.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2009-12-08
  • 最后修改日期:2010-01-22
  • 录用日期:2010-02-19
  • 在线发布日期: 2010-05-25
  • 出版日期: 2010-04-25
×
《钻探工程》期刊采编系统正在进行升级改版,部分功能正在逐步完善,在此期间给大家的使用带来不便,敬请谅解。