连拱隧道拱顶沉降数值分析
引用本文:肖林萍,李永树.连拱隧道拱顶沉降数值分析[J].测绘工程,2008,17(5):16-18.
作者姓名:肖林萍  李永树
作者单位:西南交通大学土木工程学院,四川,成都,610031;西南交通大学土木工程学院,四川,成都,610031
摘    要:在隧道施工过程中,根据现场围岩变形的监测结果,可以及时分析与预测围岩稳定性。结合小金口连拱隧道监测数据,利用数值分析方法对Ⅲ类围岩拱顶沉降位移监测数据进行处理与分析,计算得出:采用Boltzman函数拟合分析方法,能够较好地反映连拱隧道施工过程中拱顶的沉降变化情况,并得到连拱隧道拱顶沉降的控制标准。

关 键 词:连拱隧道  拱顶沉降  围岩变形  控制标准

Numerical analysis on the top subsidengce of double-arch tunnel
XIAO Lin-ping,LI Yong-shu.Numerical analysis on the top subsidengce of double-arch tunnel[J].Engineering of Surveying and Mapping,2008,17(5):16-18.
Authors:XIAO Lin-ping  LI Yong-shu
Institution:XIAO Lin-ping, LI Yong-shu ( School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, China)
Abstract:According to result of monitored and measured surrounding rock deformation, stability of surrounding rock is analyzed and predicted in the construction of the tunnel. Arch-top subsidence is calculated and analyzed in surrounding rock types Ⅲ by monitored and measured data of XIAOJINKOU double-arch tunnel in the paper. Regression analysis by Boltzman function can reflect the change of arch-top subsidence in double-arch tunnel construction. So arch-top subsidence control base of double-arch tunnel has been suggested.
Keywords:double-arch tunnel  arch-top subsidence  surrounding rock deformation  control base