南水北调西线工程地质灾害刍议
引用本文:张咸恭.南水北调西线工程地质灾害刍议[J].中国地质灾害与防治学报,2001,12(2):1-6.
作者姓名:张咸恭
作者单位:中国地质大学,
摘    要:文中详细介绍了南水北调西线工程的意义、工程简况和规划阶段对调水区工程地质条件的了解.在此基础上对该区可能遇到的地质灾害作了预测和分析.如枢纽工程可能遇到的地质灾害有断裂活动与地震灾害、冻土与冻害、坝基坝肩岩体变形破坏、滑坡泥石流灾害.线路工程以深埋、特长隧洞为主,可能遇到的地质灾害有隧洞围岩变形、活断层与震害、地温热害、涌水突泥,以及高地应力和岩爆等.并认为只要加强勘察研究,这些灾害是可以克服的.

关 键 词:南水北调西线工程  工程地质条件  地质灾害  活动断裂
文章编号:1003-8035(2001)02-0001-06
修稿时间:2001年3月28日

Preliminary discussion on geological hazards in Western Route Project for Transferring Water from Southern to Northern China
Zhang Xiangong.Preliminary discussion on geological hazards in Western Route Project for Transferring Water from Southern to Northern China[J].The Chinese Journal of Geological Hazard and Control,2001,12(2):1-6.
Authors:Zhang Xiangong
Abstract:This paper introduced the meaning,chief situations of the engineering,and the understanding of engineering geological conditions in planning stage of Western Route Project for Transferring Water from Southern to Northern China.On basis of these,the paper predicted and analysisted the geological hazards possiblly encountered in region of water transferring.For control projects,the geological hazards may be encountered are:hazards caused by fault activities and earthquakes,hazard caused by permafrost and freeze injury,hazards caused by deformation of dam foundation and abutment,landslides and debrisflows.The route projects are chiefly long tunnels with great burried depth,the hazards may be encountered for them are:deformation and failure of tunnel surrounding rockmass,hazards caused by faults activities and earthquakes,high earth temperature and hot injurg,bursting of high pressure water and mud,high earth pressure and rock blasting,etc.These geological hazard are serious for Western Route Project,but it can be overcome so long as the investigation and exploratory works are strengthened and continued.