隧道结构断面测量方法及对比分析
引用本文:杨志坚.隧道结构断面测量方法及对比分析[J].测绘通报,2019,0(11):160-162.
作者姓名:杨志坚
作者单位:甘肃铁道综合工程勘察院有限公司,甘肃 兰州,730000
摘    要:隧道结构断面测量的目的是准确测出隧道开挖的实际轮廓线,并与设计轮廓线进行对比分析,从而计算超欠挖量。断面测量根据使用的仪器不同主要有断面仪法、全站仪法和三维激光扫描仪法,本文对这3种方法的工作效率及测量精度等情况进行了对比分析,并得出了一些有益的结论。

关 键 词:三维激光扫描技术  全站仪  隧道断面  超欠挖
收稿时间:2019-05-31

Methods and comparative analysis of tunnel structure section measuring
YANG Zhijian.Methods and comparative analysis of tunnel structure section measuring[J].Bulletin of Surveying and Mapping,2019,0(11):160-162.
Authors:YANG Zhijian
Institution:Gansu Railway Survey Institute Co., Ltd., Lanzhou 730000, China
Abstract:The purpose of tunnel section measurement is to accurately measure the actual contour of the tunnel excavation and compare it with the design contour to calculate the over-underage. Section measurement according to the different instruments used, there are mainly cross-section method, total station method and 3D laser scanner method. This paper compares the working efficiency and measurement accuracy of these three methods, and draws some useful results in conclusion.
Keywords:3D laser scanning technology  total station profiler  tunnel section  overbreak-shortbreak  