首页 | 本学科首页   官方微博 | 高级检索  
     检索      

全过程的沉降量预测方法研究
引用本文:宰金珉,梅国雄.全过程的沉降量预测方法研究[J].岩土力学,2000,21(4):322-325.
作者姓名:宰金珉  梅国雄
作者单位:1. 南京建筑工程学院,江苏南京 210009
2. 河海大学岩土工程研究所,江苏南京 210098
摘    要:根据全过程的沉降量与时间关系的特点,建立了泊松曲线预测模型,然后将该模型应用于某些具体的工程,证实了该方法的合理性,最后指出了值得进一步研究的问题。

关 键 词:泊松曲线  预测模型  沉隆量  时间  测量误差  机理
文章编号:1000-7598-(2000)04-0322-04
修稿时间:2000年2月18日

Forecast method of settlement during the complete process of construction and operation
ZAI Jin-min,MEI Guo-xiong.Forecast method of settlement during the complete process of construction and operation[J].Rock and Soil Mechanics,2000,21(4):322-325.
Authors:ZAI Jin-min  MEI Guo-xiong
Abstract:Based on the settlement-time relation during the whole process of construction and operation, forecast model of Poisson curve is established. Then the model is used to forecast some projects. These forecast results prove the reasonableness of the model. In the end, the worth researching problem is pointed out.
Keywords:poisson curve  forecast model  settlement-time relation
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号