某电厂水库岸边取水工程施工实践
引用本文:李建斌,刘国谋,赵存宝,李丽,袁慧敏.某电厂水库岸边取水工程施工实践[J].探矿工程,2014,41(2):74-77,81.
作者姓名:李建斌  刘国谋  赵存宝  李丽  袁慧敏
作者单位:河南省郑州地质工程勘察院,河南郑州450053
摘    要:为满足某电厂供水需求,需在某水库进行岸边取水工程(含取水竖井、引水隧道、引水明渠3部分)施工。通过短段掘砌逆作工艺,井筒壁溶洞导水并将导出的水作为水源的一部分,实现了井筒干封底,顺利完成井筒施工;采用顶管技术+管顶注浆技术在破碎岩体、涌水量较大地层成功完成引水隧道施工;通过岩塞爆破成功实现引水隧道和水库的连接;通过船载冲击成槽技术,实现了引水明渠的施工。

关 键 词:取水工程  短段掘砌  逆作法  导水  干法封底  隧道顶管  冲击成槽
收稿时间:2013/10/17 0:00:00
修稿时间:2013/10/17 0:00:00

Construction Practice of Water Intake Engineering near the Reservoir
LI Jian-bin,LIU Guo-mou,ZHAO Cun-bao,LI Li and YUAN Hui-min.Construction Practice of Water Intake Engineering near the Reservoir[J].Exploration Engineering(Drilling & Tunneling),2014,41(2):74-77,81.
Authors:LI Jian-bin  LIU Guo-mou  ZHAO Cun-bao  LI Li and YUAN Hui-min
Institution:(Zhengzhou Institute of Geological Engineering Investigation of Henan Province, Zhengzhou Henan 450053, China)
Abstract:To meet the water supply demand of a power plant, the water intake engineering construction ( containing water intake shaft, draw water tunnel and open diversion channel) at a reservoir was needed.By means of the top-down method of excavation with lining alternated in short segments, guiding cavern water from shaft wall was derived as a part of the water source, and the shaft construction was completed with dry bottom-sealing.By pipe jacking and pipe top grouting technolo-gies, draw water tunnel was accomplished in the strata with broken rocks and abundant water inflow;by the rock plug blas-ting, the connection of the tunnel and the reservoir was successfully realized;and by percussive trenching technology, open diversion channel was constructed.
Keywords:water intake engineering  excavation with lining alternated in short segments  top-down method  guiding wa-ter  dry bottom-sealing  pipe jacking in tunnel  percussive trenching