首页 | 本学科首页   官方微博 | 高级检索  
     检索      

船载水岸一体测量技术在码头改造工程中新应用
引用本文:管明雷,陈智鹏,李清泉,朱家松.船载水岸一体测量技术在码头改造工程中新应用[J].测绘通报,2019,0(2):113-116.
作者姓名:管明雷  陈智鹏  李清泉  朱家松
作者单位:深圳大学海岸带地理环境监测国家测绘地理信息局重点实验室,广东 深圳,518060;深圳大学海岸带地理环境监测国家测绘地理信息局重点实验室,广东 深圳518060;武汉大学测绘遥感信息工程国家重点实验室,湖北 武汉430079
基金项目:深圳市科创委深港创新圈项目(SGLH20150206152559032);深圳市未来产业"创新链+产业链"融合专项扶持计划(201507211219247860)
摘    要:深圳港妈湾港区海星码头1#~4#泊位旧码头拆除工程实施过程中,为了防止在原码头深底层保留桩柱对新建桩柱的影响,需要对原码头桩柱泥面以下位置进行精密测量。本文采用船载综合测量系统水上水下一体化测量技术对妈湾港1#~4#泊位桩柱进行了水岸一体化高精度测量,通过利用激光扫描仪和多波束分别测量出水上、水下桩柱引水面点云图。基于高精度水面点云绝对坐标对水上、水下桩柱引水面点云进行特征拼接,从而获得桩柱引水面高精度绝对位置。然后根据引水面绝对位置和桩柱尺寸精准计算出保留桩柱泥面以下部分的点位和斜率。经过外符合精度验证,桩柱定位的绝对精度为10 cm。最后,将旧桩柱测量结果与新桩柱设计结果对比,结果表明:新旧桩柱在2#泊位存在一个桩柱发生碰撞,4#泊位存在10根桩柱新旧桩柱水平间隔小于10 cm,在施工过程中可能会发生碰撞。

关 键 词:多波束测量  水岸一体测量  码头桩柱测量
收稿时间:2018-05-28
修稿时间:2018-11-14

New application of ship-borne combined laser and bathymetric surveying technique in wharf reconstruction project
GUAN Minglei,CHEN Zhipeng,LI Qingquan,ZHU Jiasong.New application of ship-borne combined laser and bathymetric surveying technique in wharf reconstruction project[J].Bulletin of Surveying and Mapping,2019,0(2):113-116.
Authors:GUAN Minglei  CHEN Zhipeng  LI Qingquan  ZHU Jiasong
Institution:1. Key Laboratory for Geo-Environmental Monitoring of Coastal Zone of the National Administration of Surveying, Mapping and GeoInformation, Shenzhen University, Shenzhen 518060, China; 2. State Key Laboratory of Information Engineering in Surveying, Mapping and Remote Sensing, Wuhan University, Wuhan 430079, China
Abstract:In the process of the demolition of the old pile of Haixing pier in Shenzhen Mawan port, to avoid the remaining pile collide with the on the new pile in the new construction of the wharf, it is necessary to make a precise position of the remaining pile. The position of the remaining pile can be accurately calculated by knowing the point location and the pile slope. In this paper, the ship-borne combined laser and bathymetric surveying technique is used to survey the point location and the pile slope of the remaining pile. We used the laser scanner and multi-beam system to measure the point cloud of the water diversion surface of the pile on the water and underwater, respectively. We used the absolute coordinates of the laser point cloud with high accuracy, the point cloud of the water surface of the underwater pile is jointed, and the high precision absolute position of the water surface of the pile is obtained. Then, according to the absolute position of the water surface and the size of the pile, the point and slope of the part below the mud surface of the piles are calculated accurately. Absolute accuracy of pile positioning is 10 cm, which is verified by the location of wharf characteristic points. Finally, the measurement results of the old piles are compared with the design results of the new pile. The results show that there is a collision between new and old piles in the berth 2#, and 10 new piles and old piles in the berth 4# with a horizontal interval of less than 10 cm, which may occur in the construction process.
Keywords:multi-beam measurement  ship-borne combined laser and bathymetric surveying  wharf pile surveying  
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《测绘通报》浏览原始摘要信息
点击此处可从《测绘通报》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号